Authorisation for Solar Power Systems
In order to have the Solar Power System connected so that it can feed in electricity to the grid, the authorisation of the power supplier is required.
Once the Solar Power System has been installed, a new contract is needed with the energy supplier, and the meter needs to be replaced.
A Solar Power System with a performance that does not exceed 50 KvA is regarded as a household-sized small power plant.
The authorisation and installation procedure for the project:
Authorisation of solar power systems: EON
Payment of the first installment.
Completed forms: power of attorney, data for planning, statements of consent from the co-owner.
We submit the request to the service provider.
Typically 2-3 weeks.
We submit the connection documentation to the service provider.
The license is received from the service provider.
Payment of the second installment.
Solar Power System installation on site.
Reporting to the service provider that the system is ready.
Authorisation of Solar Power systems: ELMŰ, NKM
Payment of the first installment.
Completed forms: power of attorney, data for planning, statements of consent from the co-owner, title deed, map copy.
We submit the request to the service provider.
Typically 2-3 weeks.
Return of documents signed by the customer to the service provider: technical and economic information, producer's declaration.
The license is received from the service provider. It can be 2-3 weeks.
Payment of the second installment.
Solar Power System installation on site.
Reporting to the service provider that the system is ready.