Authorisation for Solar Power Systems

In order to have the Solar Power System connected to the grid so that it can feed in electricity, the authorisation of the power supplier is required. Once the Solar Power System has been installed, a new contract is needed with the energy supplier, and the meter needs to be replaced.

A Solar Power System with a performance that does not exceed 50 KvA is regarded as a household-sized small power plant.

The authorisation/installation procedure is as follows:

Authorisation for solar power systems: EON

First installment

Payment of the first installment.

Request completed forms

Completed forms: power of attorney, data for planning, statements of consent from the co-owner.

Claim

We submit the claim to the service provider.

Preliminary information for the service provider

It can be 2-3 weeks.

Connection documentation

We submit the connection documentation to the service provider.

License

The license is received from the service provider.

Second installment

Payment of the second installment.

Installation

Solar Power System installation on site. Report to the service provider ready that day.

Clock change
Service provider clock exchange.
Third installment
After the payment of the third installment, we will also issue the final invoice.

Authorisation for solar power systems: ELMŰ, NKM

First installment

Payment of the first installment.

Request completed forms

Completed forms: power of attorney, data for planning, statements of consent from the co-owner, title deed, map copy.

Claim

We submit the claim to the service provider.

Preliminary information for the service provider

It can be 2-3 weeks.

Return documents

Return of documents signed by the customer to the service provider: technical and economic information, producer's declaration.

License

The license is received from the service provider. It can be 2-3 weeks.

Second installment

Payment of the second installment.

Installation

Solar Power System installation on site. Report to the service provider ready that day.

Clock change
Service provider clock exchange. It can take 3-4 weeks.
Third installment
After the payment of the third installment, we will also issue the final invoice.