Authorisation for Solar Power Systems

In order to have the Solar Power System connected to the grid so that it can feed in electricity, the authorisation of the power supplier is required. Once the Solar Power System has been installed, a new contract is needed with the energy supplier, and the meter needs to be replaced.

A Solar Power System with a performance that does not exceed 50 KvA is regarded as a household-sized small power plant.

The authorisation/installation procedure is as follows:

Authorisation for solar panel systems: EON

First installment
Payment of the first installment
Request completed forms
Completed forms: power of attorney, data for planning, statements of consent from the co-owner
Claim
We submit the claim to the service provider
2-3 week
Preliminary information for the service provider
It can be 2-3 weeks
2-3 week
Connection documentation
We submit the connection documentation to the service provider
1-2 week
License
The license is received from the service provider
1-2 week
Second installment
Payment of the second installment
1 day
Installation
Solar Power System installation on site. Report to the service provider ready that day.
1 day
3-4 week
Clock change
Service provider clock exchange
3-4 week
Third installment
After the payment of the third installment, we will also issue the final invoice.

Authorisation for solar panel systems: ELMŰ, NKM

First installment
Payment of the first installment
Request completed forms
Completed forms: power of attorney, data for planning, statements of consent from the co-owner, title deed, map copy
Claim
We submit the claim to the service provider
2-3 week
Preliminary information for the service provider
It can be 2-3 weeks
2-3 week
Return documents
Return of documents signed by the customer to the service provider: technical and economic information, producer's declaration
1-2 week
License
The license is received from the service provider
1-2 week
Second installment
Payment of the second installment
1 day
Installation
Solar Power System installation on site. Report to the service provider ready that day.
1 day
3-4 week
Clock change
Service provider clock exchange
3-4 week
Third installment
After the payment of the third installment, we will also issue the final invoice.